Timeline

  1. 01.
    October 2023

    Pre-submission consultation

  1. 02.
    November 2023

    Finalise proposed design

    In Progress
  2. 03.
    November / December 2023

    Submit a planning application

    In Progress
  3. 04.
    May 2024

    Planning decision (approximately 13 weeks from submission)

    In Progress
  4. 05.
    Summer 2025

    Construction (earliest date of construction - if approval granted)

    In Progress

Additional Information

We have now submitted a full planning application to South Kesteven District Council (application reference number: S23/2199). Please find the link here: https://prod.publicaccess.southkesteven.gov.uk/online-applications/applicationDetails.do?activeTab=summary&keyVal=S4W79GONKPM00